|
Date: 20 March 2010 |
 |
 |
 |
|
Pavilion exterior |
Pavilion exterior |
Journey: "Waverock" |
|
 |
 |
 |
|
Journey: "Sisters" |
Journey: "Nation" |
Enjoy: Flower Pods |
|
 |
|
|
|
Journey: Bedrock |
|
|
|
|
Date: 2 March 2010 |
 |
 |
 |
|
Pavilion exterior |
Journey: "Sisters" |
Pavilion exterior at night |
|
 |
 |
 |
|
Pavilion exterior at night |
Pavilion exterior |
Pavilion exterior |
|
|
Date: 24 February 2010 |
 |
 |
 |
|
Journey |
Journey: Nation |
Journey: Nation |
|
 |
 |
 |
|
Journey |
Pavilion exterior |
Journey: Waverock |
|
 |
 |
 |
|
Discover |
Discover |
Pavilion entrance |
|
|
Date: 9 February 2010 |
 |
 |
 |
|
9th Feb. 10 ACT 1 - Welcome |
9th Feb. 10 ACT 2 - Upholstered Seat |
9th Feb. 10 ACT 3 - Grey film to acrylic |
|
 |
 |
 |
|
9th Feb. 10 Construction Site Overall View 01 |
9th Feb. 10 Construction Site Overall View 02 |
9th Feb. 10 Construction Site Overall View 03 |
|
 |
 |
 |
|
9th Feb. 10 Construction Site Overall View 04 |
9th Feb. 10 L3 - Function Room & Marble Wall |
9th Feb. 10 L1 - Passage |
|
 |
 |
 |
|
9th Feb. 10 L1 - VIP Lift |
9th Feb. 10 L2 - VIP Meeting Room |
9th Feb. 10 L2 - VIP Office |
|
|
Date: 19 January 2010 |
 |
 |
 |
|
19th Jan. 10 Construction Site Overall View 01 (Looking south / west) |
19th Jan. 10 Construction Site Overall View 02 (Looking south / east from pedestrian walkway) |
19th Jan. 10 Construction Site Overall View 03 (looking north / east) |
|
 |
 |
 |
|
19th Jan. 10 Construction Site Overall View 04 (West from Lupu Bridge) |
19th Jan. 10 L1 VIP - Art Niche |
19th Jan. 10 L1 VIP - Ceiling Discs Troughs and Glass Partitions |
|
 |
 |
 |
|
19th Jan. 10 Ramp - Perforated Aluminium Ceiling Installation |
19th Jan. 10 ACT 2 Theatre - Rails finished |
19th Jan. 10 E6 Preshow - Self-leveling for carpet floor |
|
 |
 |
 |
|
19th Jan. 10 Staircases - Staircase 4 Ceiling and wall finished |
19th Jan. 10 L3 VIP Area - Acoustic panel ceilings' installation |
19th Jan. 10 L3 VIP Area - Marble Wall is being installed |
|
|
Date: 5 January 2010 |
 |
 |
 |
|
5th Jan. 10 ACT 2 - Rails and Acoustic Doors installations are complete and acoustic wall panels are being installed |
5th Jan. 10 ACT 3 Marble Floor Paving is completed and protected |
5th Jan. 10 Ramp perforated panels is being installed |
|
.jpg) |
.jpg) |
.jpg) |
|
5th Jan. 10 Construction Site Overall View 01 (Looking south-west) |
5th Jan. 10 Construction Site Overall View 02 (Looking south-east from pedestrian walkway) |
5th Jan. 10 Construction Site Overall View 03 (looking north-east) |
|
 |
 |
 |
|
5th Jan. 10 L3 - Function Room Ceiling is sheeting |
5th Jan. 10 L3 - Kitchen Area Tiling |
5th Jan. 10 L2 - Ceiling support frame is being installed |
|
|
Date: 22 December 2009 |
 |
 |
 |
|
22nd Dec. 09 ACT 2 - Theatre Rails being installed |
22nd Dec. 09 L1 VIP - Ceiling starting 1st coating |
22nd Dec. 09 Act 3 - Paving being installed |
|
 |
.jpg) |
.jpg) |
|
22nd Dec. 09 L3 VIP - Function Room Passage Start Sheeting |
22nd Dec. 09 Construction Site Overall View 01 (Looking south-west) |
22nd Dec. 09 Construction Site Overall View 02 (Looking south-east from pedestrian walkway) |
|
 |
.jpg) |
 |
|
22nd Dec. 09 Lift Commissioning |
22nd Dec. 09 Construction Site Overall View 04 (looking west) |
22nd Dec. 09 L3 VIP - Lounge Room Ceiling Grids Finish |
|
 |
 |
|
|
22nd Dec. 09 Exhibition Installations - E4 Land - Wave |
22nd Dec. 09 Tube Bulkhead Finished - Tube 4 |
|
|
|
Date: 14 December 2009 |
 |
 |
 |
|
14th Dec. 09 L3 VIP - Function Room Ceiling Grids |
14th Dec. 09 ACT 2 - Theatre Rails being installed |
14th Dec. 09 Public Entrance 1 |
|
 |
.jpg) |
 |
|
14th Dec. 09 ACT 2 - Theatre Stake Holder Sheeting & Exit 1 Ceiling Grids |
14th Dec. 09 Construction Site Overall View 01 (Looking south-west) |
14th Dec. 09 Tube 5~8 Bulkhead Sheeted - Tube 7 |
|
 |
 |
.jpg) |
| 14th Dec. 09 L3 VIP - Lounge Room Ceiling Grids and Wall Substrate |
14th Dec. 09 L1 Kitchen - servery being set |
14th Dec. 09 Construction Site Overall View 06 (view from the Lupu Bridge south east) |
|
.jpg) |
 |
|
|
14th Dec. 09 Construction Site Overall View 05 (looking east) |
14th Dec. 09 E6 - Preshow 2 Painting |
|
|
|
Date: 07 December 2009 |
 |
 |
 |
|
7th Dec. 09 Construction Site Overall View 01 |
7th Dec. 09 Construction Site Overall View 02 |
7th Dec. 09 Construction Site Overall View 03 |
|
 |
 |
 |
|
7th Dec. 09 Construction Site Overall View 04 |
7th Dec. 09 Courtyard Screed Finish |
7th Dec. 09 VIP Function Room Dry Wall |
|
 |
 |
|
|
7th Dec. 09 Tube 8 Bulkhead Finish |
7th Dec. 09 Pre-show 3 Painting |
|
|
|
Date: 30 November 2009 |
 |
 |
 |
|
30th Nov. 09 ACT 1 - E1 Bedrock Ceiling Finish |
30th Nov. 09 Ramp 5 Installation |
30th Nov. 09 ACT 3 Scaffolds Strip off 001 |
|
 |
 |
 |
|
30th Nov. 09 Level 2 Office Dry Wall |
30th Nov. 09 Construction Site Overall View 01 |
30th Nov. 09 Construction Site Overall View 02 |
|
 |
 |
 |
|
30th Nov. 09 L1 VIP Entry Ceiling Sheeting |
30th Nov. 09 L1 VIP Entrance Canopy |
30th Nov. 09 East Balcony Ceiling Finish |
|
|
Date: 17 November 2009
|
 |
 |
 |
|
17th Nov. 09 Construction Site Overall View 01 & East Balcony |
17th Nov. 09 Construction Site Overall View 02 |
17th Nov. 09 Construction Site Overall View 03 |
|
 |
 |
 |
|
17th Nov. 09 Construction Site Overall View 04 |
17th Nov. 09 VIP Area L1 Lighting Slot Installation |
17th Nov. 09 ACT 1 - E1 Bedrock Light gauge Steel Joist Finish |
|
 |
 |
 |
|
17th Nov. 09 ACT 3 - Acoustic Panel Wall Installation |
17th Nov. 09 Ramp Down |
17th Nov. 09 ACT 1 - E4 Land Ceiling Finish |
|
 |
 |
 |
|
17th Nov. 09 ACT 1 - E5 People Ceiling Finish |
17th Nov. 09 L2 Offices |
17th Nov. 09 L3 Kitchen Light gauge Steel Joist |
|
 |
|
|
|
17th Nov. 09 ACT 2 - Theatre Exit Air Duct Installation |
|
|
|
|
Date: 23 September 2009 |
 |
 |
 |
|
Construction Site Overall View - South |
Construction Site Overall View - West |
Construction Site Overall View - North |
|
 |
 |
 |
|
Construction Site Overall View - East |
Public Entrance |
Glazed tube strap with paint |
|
 |
 |
 |
|
Partition wall frame steel |
Insulation |
HVAC ducts above function room |
|
|
Date: 14 September 2009 |
 |
 |
 |
|
Construction Site Overall View - South |
Construction Site Overall View - West |
Construction Site Overall View - North |
|
 |
 |
 |
|
Construction Site Overall View - East |
Public Entrance and Scaffolding Inside of Building |
Glazed Tube Ramp looking north towards the welcome area and ACT 1 beyond |
|
 |
 |
 |
|
Plant Room Cover - Frame & Purlin |
Act 2 - Scaffolding in Act 3 and Interior Façade Mullions |
Glazed Tube Helix Strap on the eastern side |
|
|
Date: 01 September 2009 |
 |
 |
 |
|
Construction Site Overall View - South |
Construction Site Overall View - West |
Construction Site Overall View - North |
|
 |
 |
 |
|
Construction Site Overall View - East |
Public Entrance |
Weathering Steel Wall |
|
 |
 |
 |
|
3 Circular lighting bars above Act 2 |
Plant Room |
Stage Staircase |
|
|
Date: 25 August 2009 |
 |
 |
 |
|
Construction Site Overall View - South |
Construction Site Overall View - West |
Construction Site Overall View - North |
|
 |
 |
 |
|
Ramp 1 |
Weathering Steel Wall |
Ramp 3 |
|
 |
 |
 |
|
Weathering Steel Wall - 2 |
Weathering Steel Wall - 3 |
Ramp |
|
|
Date: 18 August 2009 |
 |
 |
 |
|
Construction Site Overall View - South |
Construction Site Overall View - West |
Construction Site Overall View - North |
|
 |
 |
 |
|
Construction Site Overall View - East |
Roof panel and parapet wall panel - 1 |
Weathering Steel Wall - 2 |
|
 |
 |
 |
|
Level 3 Theatre - Bird Cage 2 |
Ramp 2 |
Waterproofing on the RC roof |
|
 |
 |
 |
|
Level 2 Pantry Block Wall |
Level 2 Scaffolds Building |
Level 3 Theatre - Bird Cage 1 |
|
|
Date: 5 August 2009 |
 |
 |
 |
|
Construction Site Overall View - South |
Construction Site Overall View - West |
Construction Site Overall View - North |
|
 |
 |
 |
|
Construction Site Overall View - East |
Waterproofing metal - 1 |
Act 1 - Tube steel and Helix strap 1 |
|
 |
 |
 |
|
Vertical girt for public entrance |
Act 3 - Bondek of stage paltform |
Act 1 - Bondek of ramp |
|
|
Date: 27 July 2009 |
 |
 |
 |
|
Construction Site Overall View - South |
Construction Site Overall View - West |
Construction Site Overall View - North |
|
 |
 |
 |
|
Construction Site Overall View - East |
Main Entrance |
Vertical purlin installation for external corten wall |
|
 |
 |
 |
|
Exterior block wall at ground floor |
Level 2 concrete pouring finished |
Level 3 concrete pouring finished |
|
 |
 |
 |
|
Concrete pouring for theatre slab finished |
Concrete pouring finished for vent holes for theatre |
Ramp beam finish |
|
 |
|
|
|
Glazed Tube Installation Starting |
|
|
|
|
Date: 14 July 2009 |
 |
 |
 |
|
Parapet Wall - South View |
Construction Site Overall View - West |
Parapet Wall - East View |
|
 |
 |
 |
|
Construction Site Overall View - East |
Main Entrance |
Roof Panel |
|
 |
 |
|
|
Theatre Vents |
Parapet Wall - West View |
|
|
|
Date: 15 June 2009 |
 |
 |
 |
|
Construction Site Overall View - East |
Theatre Area L3 and Roof Safety Net Ready |
Theatre L2 Concrete Slab Poured |
|
Date: 6 May 2009 |
 |
 |
 |
|
Theatre area structural steel with main roof |
Structural steel overall view |
Construction site overall view |
|
 |
 |
|
|
Steel column delivered to site |
Site entrance |
|
|
Date: 29 April 2009 |
 |
 |
|
Installation of the 7Tonne rafters
|